As a testament to my obsession with progress bars in R, here is a quick investigation about the overhead cost of drawing a progress bar during computations in R. I compared several approaches including my pbapply and Hadley Wickham’s plyr.
Let’s compare the good old lapply
function from base R,
a custom-made variant called lapply_pb
that was
proposed here, l_ply
from the plyr package,
and finally pblapply
from the pbapply package:
library(pbapply) library(plyr) lapply_pb <- function(X, FUN, ...) { env <- environment() pb_Total <- length(X) counter <- 0 pb <- txtProgressBar(min = 0, max = pb_Total, style = 3) wrapper <- function(...){ curVal <- get("counter", envir = env) assign("counter", curVal +1 ,envir = env) setTxtProgressBar(get("pb", envir = env), curVal + 1) FUN(...) } res <- lapply(X, wrapper, ...) close(pb) res } f <- function(n, type = "lapply", s = 0.1) { i <- seq_len(n) out <- switch(type, "lapply" = system.time(lapply(i, function(i) Sys.sleep(s))), "lapply_pb" = system.time(lapply_pb(i, function(i) Sys.sleep(s))), "l_ply" = system.time(l_ply(i, function(i) Sys.sleep(s), .progress="text")), "pblapply" = system.time(pblapply(i, function(i) Sys.sleep(s)))) unname(out["elapsed"] - (n * s)) }
Use the function f
to run all four variants. The expected run time
is n * s
(number of iterations x sleep duration),
therefore we can calculate the overhead from the
return objects as elapsed minus expected. Let’s get some numbers
for a variety of n
values and replicated B
times
to smooth out the variation:
n <- c(10, 100, 1000) s <- 0.01 B <- 10 x1 <- replicate(B, sapply(n, f, type = "lapply", s = s)) x2 <- replicate(B, sapply(n, f, type = "lapply_pb", s = s)) x3 <- replicate(B, sapply(n, f, type = "l_ply", s = s)) x4 <- replicate(B, sapply(n, f, type = "pblapply", s = s)) m <- cbind( lapply = rowMeans(x1), lapply_pb = rowMeans(x2), l_ply = rowMeans(x3), pblapply = rowMeans(x4)) op <- par(mfrow=c(1, 2)) matplot(n, m, type = "l", lty = 1, lwd = 3, ylab = "Overhead (sec)", xlab = "# iterations") legend("topleft", bty = "n", col = 1:4, lwd = 3, text.col = 1:4, legend = colnames(m)) matplot(n, m / n, type = "l", lty = 1, lwd = 3, ylab = "Overhead / # iterations (sec)", xlab = "# iterations") par(op) dev.off()
The plot tells us that the overhead increases linearly
with the number of iterations when using lapply
without progress bar.
All other three approaches show similar patterns to each other
and the overhead is constant: lines are
parallel above 100 iterations after an initial increase.
The per iteration overhead is decreasing, approaching
the lapply
line. Note that all the differences are tiny
and there is no practical consequence
for choosing one approach over the other in terms of processing times.
This is good news and another argument for using progress bar
because its usefulness far outweighs the minimal
(<2 seconds here for 1000 iterations)
overhead cost.
As always, suggestions and feature requests are welcome. Leave a comment or visit the GitHub repo.